This will truly be a stick-built house. They spent all day measuring and cutting all the pieces needed to assemble your house. Middle pieces are all neatly stacked and labeled, and edge pieces are laid out in their proper places.
Author: dreaminofobx
June 21-Floored
The framing crew worked hard and got the sub-floor laid before the incoming tropical storm. AdvanTech won’t even blink at 3″ of rain.
June 12–Dirt work
They brought in trucks full of dirt and gravel to do the preliminary grading on your lot. The driveway is nearly flat, and slopes just slightly from right to left. The front yard on the guest bedroom side slopes steeply down from the sidewalk/driveway.
June 8–French drain and crawlspace pad
June 7–Waterproofing
June 6–More foundation work

After the weekend and more than 1.5 inches of rain, the crew was able to finish laying the foundation today.
June 1–Foundation work begins
May 30–Footers poured
May 28–Storm damage
May 19–High volume expected?

An additional porta-potty has been delivered. Must be expecting an abundance of laborers in the coming weeks?