July 25–Windows, doors, decking & blocking

All windows and doors are installed. Exterior color is light (putty?).

Trex decking has been installed (this will get covered to protect it during the rest of the exterior work).

Blocking has been added at appropriate heights.

IMG_0356
Supplies for electrical rough-in have been delivered. These are all builder-supplied materials, none of your fixtures are/will be stored in the unsecured house.

July 11–More framing

There was an awful lot of banging today, but little visual evidence of the work that was done. Putting up walls was pretty dramatic; now that they are into the detail work, progress is a little less obvious.

June 29–Stopping point

The framing crew is basically stuck until the trusses for the second floor are delivered. All of the first floor walls are up, and the staircase is in place, but the crane operator is off for a long holiday weekend and won’t be available until Wednesday.