September 14–Big changes in the past week

Returned from a week in VA to find much progress outside.

 

With tropical storm remnants from Harvey and Irma passing through, it’s been pretty rainy for nearly 10 days. There is still water seeping into the crawl space, but gutter installation should solve this problem.

IMG_1053

 

Meanwhile, on the inside, insulation is complete.

 

The gap in the exterior wall of the sunroom has been fixed, and the master closet door opening has been reframed to the correct size.

August 19–Rough-ins complete

The garage floor has cured and is now covered.

IMG_0835

Plumbing and electrical rough-ins are complete. See video tours of house and crawl space on CD for more detailed visuals on exact location of wires and pipes within walls/ceiling.

August 15–Concrete, doors, crawl space

Garage floor and front porch have been poured.

 

Pocket doors and crawl space door have been delivered and await installation.

 

Preview of plumbing running through crawl space (nothing is currently intruding in the space where your concrete pad was poured).

August 3–Progress inside and out

The roof is complete!

 

Electrical rough-ins continue…

 

Plumbing rough-ins throughout the house