You got shutters…

…and a pantry…
…and a master closet (I stood in the center, started at the door, and took pictures clockwise till I got back to the door).
So much stuff going on today. We’ll start outside and work our way in. They cleared Lot 15 today, so you’ll have neighbors in about a year.
The painters returned with the correct color paint/stain for your house. The corbels have been re-stained and look good next to your gutters. The porch ceiling appears to be more paint than stain–not sure if that is the true Sherwin Williams product or if they had to get an actual paint to cover the oops stain from Friday. They brought in naked shutters from the other house, and those have been stained and are drying in your living room. Back porch ceiling has not been done yet, because Dennis and Matt were busy out there installing the porch railings.
Inside, you’ve got an oven and doorstops!
Outside, the gutters have been put up. Rain chains will be installed later.

On the inside, error correction in the guest bath. The short, stumpy shower arm has been replaced by the longer one you provided.
The heated towel bar is finally up!!!

The vent hood, range, microwave, and dishwasher are all in. I’m guessing the installer needs a second pair of hands to heft the oven up into its spot in the wall.
Wire shelving is complete in guest bedroom, coat closet, and linen closet.
Everybody is in and out, trying to finish up last minute projects. The painters are staining stair treads, hand rails, and posts.
The electricians installed more fixtures, including the stair light that had the broken glass and vanity lights in your master bath. The bathroom fan is also up, but they are waiting to put up the towel bar until the painters do some touch-up work on that wall.
The glass door has been hung on your shower. The plumbers also finished hooking up the handheld shower head.
Outside, your driveway has been graded and prepped for concrete to be poured.
Inside, the plumbers have been hard at work. All of your toilets have been relocated to their proper locations. The shower head with the extender has been installed (it does not appear to extend very much).
They have also installed the tankless water heater in the garage (vent pipes and gas line not yet hooked up).