They found the correct counter top for the guest bath and got that installed today.

They found the correct counter top for the guest bath and got that installed today.

Lots of things have been happening in the past two weeks. Outside, the dumpster has been removed (this is a sign work is in the final stages). Exterior lights were installed.
All of your interior doors were installed. Trim work was completed–windows, doors, crown moulding, baseboards, bead board, coffered ceilings.
The electricians put up the foyer light, installed the other three dimmer switches.
Vinyl flooring has been installed in the half bath. The new vanity has not arrived yet.
Countertops and sinks have been installed in the kitchen, master bath, and guest bath.
There’s been 1.75″ of rain since midnight, so I did not slog around to the crawl space to see if anything had changed under the house.
The master shower is all finished. There is a nice outward slope to the back cubby and the bench. The front cubby ended up just about level.
Wood floors have been installed. They are mostly covered and protected, but you can get a peek at them in the pantry and along the back wall of the kitchen where shelves/cabinets will be installed.