November 28–Tryptophan slow-down

Not too much change around the house over the last few days, thanks to the Thanksgiving holiday. There has been some progress in the master bath–floor is complete and shower walls are coming along. The special little door to the attic storage space has been delivered. Wood flooring was dropped off today, and is stacked in the guest bedroom to acclimate before installation. The masons completed the brickwork above the garage door today.