November 28–Tryptophan slow-down

Not too much change around the house over the last few days, thanks to the Thanksgiving holiday. There has been some progress in the master bath–floor is complete and shower walls are coming along. The special little door to the attic storage space has been delivered. Wood flooring was dropped off today, and is stacked in the guest bedroom to acclimate before installation. The masons completed the brickwork above the garage door today.

November 20–Miscellaneous Projects

On this afternoon’s walk-through, here’s what’s new…

You have tile floors going in. Laundry room and guest bath are complete. Master bath is still a work in progress, but they built your bench!

 

Brickwork on the exterior seems to be at a standstill around the garage…so close! No more progress inside on the fireplace, either.

IMG_2506

 

You got your garage door opener.

IMG_2497

 

Here’s what’s happening under the house…light and smoke detector are installed, and you can kinda see that your “finished” area is still clear so far.

IMG_2496

 

Meanwhile, in the attic, you got some extra blown-in insulation this week.

IMG_2504

 

And finally, your interior doors have arrived and are waiting to be installed.

IMG_2498

November 15–Lights!

Bryden and Buddy were busy while we were in OBX, installing most of your light fixtures. (Master bath, front hall, front porch, back porch fan, outdoor garage lights not installed.) Fluorescent lights are in the closets, but not pictured.