Workers finished hanging the rest of the drywall yesterday. Todd is spending today cleaning up their mess and covering the subfloor with paper in preparation for the mudders next week.
Month: September 2017
September 26–Half walls
September 24–Paint’s on, drywall’s in
September 22–Worker bees
September 14–Big changes in the past week
Returned from a week in VA to find much progress outside.
With tropical storm remnants from Harvey and Irma passing through, it’s been pretty rainy for nearly 10 days. There is still water seeping into the crawl space, but gutter installation should solve this problem.

Meanwhile, on the inside, insulation is complete.
The gap in the exterior wall of the sunroom has been fixed, and the master closet door opening has been reframed to the correct size.