Yay, the inspector has come!

And while we were waiting for him, outside work continued…
Interior work has stopped until the electrical and plumbing inspections are done. In the meantime, they are piddling with some outside work, like installing the metal accent roofing above the garage. Materials for the soffits along the eaves are waiting in the garage.
The garage floor has cured and is now covered.

Plumbing and electrical rough-ins are complete. See video tours of house and crawl space on CD for more detailed visuals on exact location of wires and pipes within walls/ceiling.
Garage floor and front porch have been poured.
Pocket doors and crawl space door have been delivered and await installation.
Preview of plumbing running through crawl space (nothing is currently intruding in the space where your concrete pad was poured).
The roof is complete!
Electrical rough-ins continue…
Plumbing rough-ins throughout the house