The fireplace is installed.
Placement of outlets, switches, and light boxes has begun throughout the house.
All windows and doors are installed. Exterior color is light (putty?).
Trex decking has been installed (this will get covered to protect it during the rest of the exterior work).
Blocking has been added at appropriate heights.

There was an awful lot of banging today, but little visual evidence of the work that was done. Putting up walls was pretty dramatic; now that they are into the detail work, progress is a little less obvious.